REQUIREMENTS FOR PERMITS

Application Letter to include Proposed routes, Routes diagram, Distance to be covered. Letter must be addressed to the General Manager, LAGOS STATE INFRASTRUCTURE MAINTENANCE & REGULATORY AGENCY.
Lists of all routes and scope of work
Site Assessment Report
Occupational Health and Safety Plan
Payment for application

SCHEDULE OF FEES FOR PERMIT

S/NACTIVITYAMOUNT (₦)
1Application Fee₦50,000.00
2Power5,800.00 / Meter
3LASIMRA  Administrative and Project Management fees applicable in all LASIMRA activities outline above15% of Permit fees

P

SCHEDULE OF FEES FOR RE-INSTATEMENT
1RE- INSTATEMENT
 PRICING
aASPHALT14,000.00/ Meter
bCONCRETE12,000.00 /Meter
cLAWN 5,000.00 / Meter
dPAVING STONE 10,000.00/ Meter
2INTEGRITY TEST
 PRICINGNIL